| ACTIVITY | ACTIVITY STATUS | ||||
| BLOCK A | BLOCK B | BLOCK C | BLOCK D | ||
| 1 | Work in foundation & plinth |
Complete |
Complete |
Complete |
Complete |
| 2 | R.C.C work |
||||
| a | Ground floor columns |
Complete |
Complete |
Complete |
Complete |
| b | Ground floor slab |
Complete |
Complete |
Complete | Complete |
| c | First floor columns |
Complete |
Complete | Complete | Complete |
| d | First floor slab |
Complete |
Complete | Complete | Complete |
| e | Second floor columns |
Complete |
Complete | Complete | Complete |
| f | Second floor slab |
Complete |
Complete |
Complete |
Complete |
| g | Sundeck + Roof Slab |
Complete |
Complete | in progress | in progress |
| h | Staircase roof slab | Complete | Complete | in progress | in progress |
| 3 | Masonary work |
||||
| a | Ground floor |
Complete |
Complete |
Complete | Complete |
| b | First floor |
Complete |
Complete |
Complete |
Complete |
| c | Second floor |
Complete |
Complete |
Complete | in progress |
| d | Terrace |
Complete |
Complete | in progress | |
| 4 | Electrical Work | ||||
| A | Conduiting & box fixing |
||||
| a | Ground Floor | Complete | Complete | Complete | Complete |
| b | First Floor | Complete | Complete | Complete |
in progress |
| c | Second Floor | Complete | Complete | Complete | |
| d | Terrace |
Complete |
in progress |
||
| 5 | Gypsum plaster |
||||
| a | Ground floor ceiling |
Complete |
Complete | Complete | |
| b | First Floor ceiling | Complete | Complete | Complete | |
| c | Second Floor ceiling | Complete | in progress | in progress | |
| d | Ground floor walls | Complete | Complete | Complete | |
| e | First Floor Walls | Complete | Complete | Complete | |
| f | Second Floor Walls |
Complete | Complete | in progress | |
| 6 | External Plaster | ||||
| a | Ground floor | Complete | in progress |
||
| b | First Floor | Complete | in progress |
||
| c | Second Floor |
Complete |
in progress |
||
| 7 | Internal plaster in bathroom & kit | ||||
| a | Ground floor |
Complete |
Complete |
||
| b | First Floor |
Complete |
Complete |
||
| c | Second Floor |
Complete |
Complete |
||
| 8 | Waterproofing | ||||
| a |
Ground floor
| Complete | Complete | in progress | |
| b |
First Floor
| Complete | Complete |
||
| c |
Second Floor
|
Complete | Complete | ||
| d | Terrace | in progress | |||
| 9 | Fabrication - Balcony railing | ||||
| a |
Ground floor
|
N.A |
N.A |
||
| b |
First Floor
| Complete | Complete | ||
| c |
Second Floor
| Complete | Complete | ||
| d | Terrace | in progress |
in progress |
||
| 10 | Plumbing | in progress | in progress | in progress | |
| complete -completed before month of June '09 | complete - in month of June '09 | in progress - in month of July '09 | |||
** The above table and the pictures gives the present status of various
construction activities on site as on 1st July 2009. The next update
will be uploaded on the website by the 2nd weekend of August. This is
for the information of the homeowners .
North West view of building A |
West view of building B |
North East view of building C |
North East view of building D |
