  ACTIVITY ACTIVITY STATUS
    BLOCK A BLOCK B BLOCK C BLOCK D
1
Work in foundation & plinth
Complete
Complete
Complete
Complete
           
2
R.C.C work
       
a
Ground floor columns
Complete
Complete
Complete
Complete
b
Ground floor slab
Complete
Complete
Complete
Complete
c
First floor columns
Complete
Complete
Complete Complete
d
First floor slab
Complete
Complete
Complete Complete
e
Second floor columns
Complete
Complete
Complete Complete
f
Second floor slab
Complete
Complete
Complete
Complete
g
Sundeck + Roof Slab
Complete
Complete
in progress in progress
h
Staircase roof slab
Complete
Complete
in progress in progress
           
3
Masonary work
       
a
Ground floor 
Complete
Complete
Complete Complete
b
First floor 
Complete
Complete
Complete
Complete
c
Second floor 
Complete
Complete
Complete in progress
d
Terrace
Complete
Complete
in progress  
           
4 Electrical Work        
A
Conduiting & box fixing
       
a
Ground Floor
Complete Complete Complete Complete
b
First Floor
Complete Complete
Complete
in progress
c
Second Floor
Complete Complete Complete  
d
Terrace
Complete
in progress
   
           
5
Gypsum plaster
       
a
Ground floor ceiling
Complete
Complete
Complete  
b
First Floor ceiling
Complete Complete Complete  
c
Second Floor ceiling
Complete in progress in progress  
d
Ground floor walls
Complete Complete Complete  
e
First Floor Walls
Complete Complete Complete  
f
Second Floor Walls
Complete Complete in progress  
           
6 External Plaster        
a
Ground floor
Complete
in progress
   
b
First Floor
Complete
in progress
   
c
Second Floor
Complete
in progress
   
           
7 Internal plaster in bathroom & kit        
a
Ground floor
Complete
Complete
   
b
First Floor
Complete
Complete
   
c
Second Floor
Complete
Complete
   
           
8 Waterproofing        
a
Ground floor
Complete
Complete
in progress  
b
First Floor
Complete
Complete
   
c
Second Floor
Complete
Complete    
d Terrace in progress      
           
9 Fabrication - Balcony railing        
a
Ground floor
N.A
N.A
   
b
First Floor
Complete Complete    
c
Second Floor
Complete Complete    
d Terrace
in progress
in progress
   
           
10 Plumbing
in progress
in progress in progress  
complete -completed before month of June '09 complete - in month of June '09 in progress - in month of July '09


** The above table and the pictures gives the present status of various construction activities on site as on 1st July 2009. The next update will be uploaded on the website by the 2nd weekend of August. This is for the information of the homeowners .


North West view of building A

West view of building B

North East view of building C

North East view of building D